FAHEY, J.
This appeal presents the question whether the mere commencement of an action seeking "rescission and/or reformation" of a contract constitutes an anticipatory breach of such agreement. Under the circumstances of this case, we conclude that it does not. We reverse the Appellate Division order and answer the certified question in the negative.
By way of background, plaintiff agreed to purchase the property in question (a developable waterfront parcel on Staten Island) from defendants Allied Princes Bay Co. and Allied Princes Bay Co. #2, L.P. (collectively, APB).
The agreement also provided that if the approvals could not be obtained by the outside closing date, then either party could terminate the agreement upon 30 days' notice. In the event of such termination, plaintiff would receive a refund of its deposit and the parties would be released from the majority of their contractual obligations. In lieu of termination, plaintiff retained an option to waive the approvals and proceed to closing.
To that end, in March 2006, APB and plaintiff amended the purchase contract to increase the purchase price and down payment to be made with respect to the property, to require the parties to share in the costs of remediation, and to extend the "Outside Closing Date" for the sale to July 22, 2007. That outside closing date later was extended — on approximately 11 occasions — to July 22, 2008, based on the ongoing nature of the remedial work required to close the sale. The amendments to the contract also contain what is referred to as a forbearance clause, which essentially provided that, "as a material inducement to [APB's] agreement to the New Outside Closing Date," plaintiff would "not ... commence any legal action against [APB] ... in the event that any of the Development Approvals ha[d] not been issued or the [remedial work] ha[d] not been completed by the New Outside Closing Date."
Approximately one month before the final new outside closing date, plaintiff commenced this action alleging, among other things, fraud in the inducement of the amendments to the contract. Plaintiff also sought to eliminate the increase in purchase price and the requirement that plaintiff share in the cost of repairs to the property, as embodied in the amendments. Said simply, plaintiff sought specific performance of the contract absent the amendments on the ground that the amendments were executed based on defendants' alleged misrepresentation of their ability to complete the remedial work necessary to close the sale.
In response, defendants (save for defendant AKRF Engineering, P.C., which did not join this motion practice)
All of plaintiff's causes of action subsequently were dismissed. The matter eventually proceeded to defendants' motion for partial summary judgment, which considered only the first and third counterclaims. Through that application, defendants sought judgment declaring that the contract is terminated, and that plaintiff materially breached the contract. Supreme Court granted the motion, adjudging that the contract had "expired by its terms" and that plaintiff "materially breached" that compact, entitling defendants to, among other things, retain the down payment and the remedial payments made pursuant to the amendments to that agreement.
On appeal, the Appellate Division affirmed the judgment insofar as appealed from
The Appellate Division subsequently granted plaintiff leave to appeal to this Court. In doing so, the Appellate Division certified for our review the question whether "the order of the
"An anticipatory breach of contract by a promisor is a repudiation of [a] contractual duty before the time fixed in the contract for ... performance has arrived" (10-54 Corbin on Contracts § 54.1 [2017]; see 13 Williston on Contracts § 39:37 [4th ed]). An anticipatory breach of a contract — also known as an anticipatory repudiation — "can be either a statement by the obligor to the obligee indicating that the obligor will commit a breach that would of itself give the obligee a claim for damages for total breach or a voluntary affirmative act which renders the obligor unable or apparently unable to perform without such a breach" (Norcon Power Partners v Niagara Mohawk Power Corp., 92 N.Y.2d 458, 463 [1998] [internal quotation marks omitted]; see 2B NY PJI2d 4:1 at 35-36 [2017]).
For an anticipatory repudiation to be deemed to have occurred, the expression of intent not to perform by the repudiator must be "positive and unequivocal" (Tenavision, Inc. v Neuman, 45 N.Y.2d 145, 150 [1978]; see Ga Nun v Palmer, 202 N.Y. 483, 489 [1911]). We have taught that the party harmed by the repudiation must make a choice either to pursue damages for the breach or to proceed as if the contract is valid (see Strasbourger v Leerburger, 233 N.Y. 55, 59 [1922]; see also American List Corp. v U.S. News & World Report, 75 N.Y.2d 38, 44 [1989]). We have also clarified that "a wrongful repudiation of the contract by one party before the time for performance entitles the nonrepudiating party to immediately claim damages for a total breach" (id.).
On this record — and particularly in view of the repeated movement of the new outside closing date — we cannot conclude that the commencement of this action reflects a repudiation of the contract. At the core of this appeal is the unsettled question whether "the commencement of an action, particularly one seeking rescission, is itself an anticipatory breach" (Princes Point, 138 AD3d at 117, citing Auten v Auten, 308 N.Y. 155, 159 [1954] [addressing whether an action for separation constituted a repudiation of a prior separation agreement, but declining to answer that question given that English law controlled that matter]). The Appellate Division correctly observes that the commencement of a declaratory judgment action "does not constitute an anticipatory breach ... because a declaratory
We do not, however, agree with the Appellate Division's conclusion that, in this context, "[a]n action seeking rescission of a contract is markedly different" from a declaratory judgment action (id.). To be sure, this action (one for "rescission and/or reformation" of the purchase agreement based on defendants' purported misrepresentation with respect to the condition of the property) and a declaratory judgment action necessarily would produce different results. This action is one based on the terms under which the amendments to the contract were entered, and essentially seeks to nullify those terms. A declaratory judgment action would produce a ruling as to the rights of the parties under the terms of the contract, and essentially would determine the meaning of those terms (see CPLR 3001 [considering declaratory judgment actions]). Nevertheless, in this context — specifically, where the amended complaint seeks, among other things, reformation of the amendments to the contract and specific performance of the original agreement — there was no "positive and unequivocal" repudiation (Tenavision, 45 NY2d at 150). There is no material difference between this action and a declaratory judgment action. At bottom, both actions seek a judicial determination as to the terms of a contract, and the mere act of asking for judicial approval to avoid a performance obligation is not the same as establishing that one will not perform that obligation absent such approval (see Restatement [Second] of Contracts § 250, Illustration 3).
Finally, with respect to plaintiff's request for "reverse" summary judgment, we note that, "[w]hile Supreme Court and the Appellate Division may search the record and grant summary judgment to a nonmoving party (see CPLR 3212 [b])," this Court may not (see JMD Holding Corp. v Congress Fin. Corp., 4 N.Y.3d 373, 385 [2005], citing Merritt Hill Vineyards v Windy Hgts. Vineyard, 61 N.Y.2d 106, 110-111 [1984]). To that end, in reversing
Accordingly, the Appellate Division order should be reversed, with costs, the motion of defendants for partial summary judgment on the third counterclaim denied, and the certified question answered in the negative.
Order reversed, with costs, motion by defendants Allied Princes Bay Co., Allied Princes Bay Co. #2, L.P., Muss Development L.L.C. and Joshua L. Muss for partial summary judgment on the third counterclaim denied, and certified question answered in the negative.